Project Description

Project Brief:

Project was Identified by PEDO-GTZ in 1998. Feasibility Study was conducted in 2008-2011. Feasibility Review was carried out in 2013-14. EPC Contract was awarded to GRC JV ( A Joint Venture of Ghulam Rasool and Company Private (Ltd);TRIED (Chinese Firm) and Hydro China (Chinese Firm) on November 13, 2014. Construction work is in progress since November 26, 2014. Project completion is expected in June 30, 2021.

Salient Features of the Project:

Capacity (MW) : 10.2

Net Head (m) : 148

Annual Energy (GWh): 71.1

Discharge (m³/s) : 8

Tunnel (m): 2895

Current Status (Completed or in Progress and percentage of progress):

In Progress, 93% Completed

Over All Progress

93 7 3

96

Land Acquisition

100

100

Detail Engineering Design

99 1 0

99

Preparatory Civil Works

100

100

Permanent Civil Works

97 3 3

100

E&M Works  (Manufacturing, Delivery & Installation)

90

Transmission Line

84 16 11

95

Power Evacuation / Other Studies / Testing

66 34 6

72